Below are some photos of the final trenching work behind the 4th green. Click on the photos for a larger version.
Update - 10 May 2012
Trenching
is already completed from the river bank to the boundary of the dairy property,
and about 300m towards MCC. They are well ahead of schedule. The pipe itself is
in place alongside the route, and will be laid and backfilled progressively
over the next week. The section from the river bank to where the control panel
will be located, is already laid, sealed and backfilled.If golfers look right from the 4th & 5th tees they will see the trucks & machinery on the hill approaching our boundary.
Today was a truly rewarding moment for us as we recalled the series of events leading to this final stage.